There is no single province-wide building permit in British Columbia: the BC Building Code sets the construction standard, and your municipality or regional district issues the permit under its own building bylaw. Find your local authority, check its bylaw, and work its application, review, and inspection sequence.
There is no single building permit for British Columbia. That sentence saves more time than any other in this guide. The province sets the construction standard through the BC Building Code, and your local authority — a municipality, a regional district, or another body the legislation names — issues the permit, reviews the drawings, inspects the work, and decides when the building may be occupied, all under its own building bylaw. Two projects that look identical can therefore follow different forms, different fees, and different timelines, because they sit in different authorities. This guide describes the sequence that is common across the province, names the points where local rules take over, and gives two municipal examples so you can see what a local process actually looks like. It does not rest on any announced change to the Code or to permitting: pledges are not law, and at the time of writing the provincial election results were still preliminary, with certification pending. The process described here is the process in force. Recheck on swearing-in and the first cabinet moves, and recheck your own authority's bylaw before you apply, because bylaws change more often than the Code does.
Step 1: Find your local authority
Start with the parcel, not the project. Identify the municipality the land sits in, or the regional district if it sits outside a municipality. That body is the permit issuer for most projects. Two exceptions are worth knowing before you go further. First, the BC Building Code applies throughout British Columbia except on some federal lands and in the City of Vancouver, which has its own building bylaw; a Vancouver project follows the Vancouver bylaw, not this guide's sequence. Second, some land is administered by other authorities named in the legislation, such as a treaty First Nation, the Nisga'a Lisims Government, or the University of British Columbia board of governors for its lands. If the land is in one of those categories, the permit route runs through that authority.
Once you have the authority, open three things: its building permit pages, its building bylaw, and its application checklist for your project type. The bylaw is the governing document. The web pages explain it; the bylaw decides it. Save or print the checklist version you worked from, with its date, because a checklist revised mid-application can change what you owe.
Step 2: Check whether your project needs a permit, and what else it needs first
Read the bylaw's permit list for your authority. New construction, additions, alterations, renovations, and demolitions commonly need a building permit, and completing an unfinished area commonly does too. Cosmetic work such as painting, flooring, replacing baseboards, and resurfacing cabinets commonly does not. But "commonly" is not a rule: the bylaw list governs, and it varies. A deck, a retaining wall, a secondary suite, a change of occupancy, and a sign can each sit on a different side of the line in different authorities.
A building permit is rarely the only approval. Before you apply, check zoning: the proposed use, height, setbacks, and site coverage must be permitted for the parcel, or the building permit review will stop at the zoning check. Check whether a development permit is required for the area, whether a development variance permit is needed for anything that does not conform to a bylaw, and whether heritage, floodplain, agricultural land, or environmental rules touch the parcel. Kelowna's pages illustrate the point: a separate application is required for each building, and materials such as a current State of Title, septic approval where applicable, and Homeowner Protection Office warranty documentation for a new home can all form part of a complete application. None of those items is a building permit, and all of them can hold one up. List every approval the project needs, in the order the authority wants them, before you spend money on drawings.
Step 3: Assemble the application package
Work from the authority's checklist, not from a generic list. A typical package includes scaled drawings, a site plan, and any schedules, letters of assurance, and supporting documents the authority requires for the project type. Kelowna's application materials show the shape of it: structural and geotechnical schedules and drawings where applicable, energy efficiency specifications, scaled drawings with site plans, a roof truss package where applicable, and a construction fire safety plan, among other items. Richmond's commercial requirements show the same pattern from the other direction: applications require all documentation and drawings listed on the application form, and incomplete applications will not be accepted.
Three habits prevent most delays. First, submit a complete package the first time: an incomplete application does not join the review queue, it waits. Second, make the drawings consistent with each other: a floor plan, a section, and a site plan that disagree on a dimension generate a review comment each. Third, name the professional work honestly: if the authority requires a schedule signed by a registered professional, that schedule must be in the package, signed, before review starts, not promised for later. Pay the application fee in the manner the authority specifies; Kelowna's pages note that payment of the fee is a required part of a complete application, with fees emailed with a link to pay online. Keep the receipt and the stamped copy of the submitted set.
Step 4: Work through review and corrections
Once accepted, the drawings are reviewed for compliance with the BC Building Code, zoning, and other bylaws. Richmond's building approvals pages describe the shape of the review: drawings are reviewed before permit issuance, the review involves different areas within the city such as health, fire, and planning, comments are compiled and forwarded to the applicant, and when all issues are resolved, a permit is issued. Your authority's version will differ in detail, but the rhythm is the same: comments come back, you answer them, you resubmit.
Answer every comment, in writing, and point to the drawing or page where each answer appears. Do not answer a structural comment verbally and assume it is recorded. Do not resubmit a whole new drawing set when the reviewer asked for one corrected sheet, unless the authority asks for the full set. If a comment asks for something you believe the Code does not require, ask for the Code reference and the bylaw reference, politely and in writing, and get the answer before you redraw. If the project changes during review — a different layout, a different occupancy, a different structural system — tell the authority promptly: a permit issued for one design does not cover a different design, and undisclosed changes discovered at inspection create a second review at the worst possible time.
Step 5: Build to the inspections
The issued permit comes with a list of required inspections. Richmond's pages state the principle that applies province-wide: at each phase of construction, inspections are required to ensure construction complies with codes and regulations and follows the approved plans, and a complete list of required inspections is provided to the applicant at permit issuance. Book each inspection when the work is ready for it, not when the next trade is scheduled to arrive. Do not cover work before its inspection: framing, insulation, plumbing rough-in, and other concealed work must be seen before it is closed in. If an inspector requires a correction, make it, and have it re-inspected before proceeding past that stage.
Keep the approved drawings on site, and build to them. The inspector works from the reviewed drawings; a field change that is not on the drawings is a deviation, even if it is an improvement. Record every inspection result, with the date and the inspector's name, in the project file. If the project will take a long time, ask the authority whether the permit has an expiry or a commencement condition, and what renews it: permit validity periods are set by bylaw, and this guide states no province-wide period because none exists.
Step 6: Occupy only when the authority says so
Occupancy is a separate approval, not the natural end of construction. Some authorities issue an occupancy permit; others issue a provisional occupancy or a final inspection sign-off. Richmond's permit pages list a provisional occupancy permit and an occupancy permit for temporary buildings among their other permits, which illustrates that occupancy approval is its own instrument with its own conditions. Ask, before construction starts, what occupancy approval your project type requires, what inspections must be complete before it issues, and whether partial or provisional occupancy is available. Do not move in, open to the public, or let a tenant occupy on the strength of a passed final inspection alone if the authority requires a separate occupancy document. Keep the issued permit, the inspection record, and the occupancy approval together: a future sale, refinancing, or insurance question will ask for them.
What this guide deliberately does not carry
This guide carries no fee figure, no timeline, and no permit validity period, because no province-wide figure exists and every authority sets its own. It carries no list of projects that never need a permit, because the bylaw list governs and varies. It carries no claim about any proposed change to the BC Building Code or to permitting processes, because no such change is stated as law on the pages checked, and the election results at the time of writing were still preliminary, with certification pending. It carries no building advice: the Code's technical requirements are a matter for the drawings and the professionals who prepare them, not for a process guide. If your authority's bylaw or the BC Codes pages change any point in this guide, the bylaw and the Code govern.
Related guides
Questions people ask
Is there one BC building permit I can apply for online?
No. British Columbia has one provincial construction standard, the BC Building Code, but no single provincial permit counter. The Building and Safety Standards Branch states plainly that it does not enforce compliance with the Code: local authorities are authorized to enforce it through the Local Government Act and the Community Charter. In practice that means your municipality issues the permit under its building bylaw, a regional district issues it outside municipal boundaries, and the City of Vancouver is the exception that proves the rule, because the BC Codes do not apply there and Vancouver has its own building bylaw. Start by identifying the local authority for the parcel, then open that authority's building permit pages and its building bylaw. Any guide, contractor, or form that promises a province-wide permit is describing something that does not exist.
Does every renovation need a permit?
No, and no single province-wide list decides it. Your local authority's building bylaw is the list that matters. Richmond's building approvals pages, for example, say permits are required to construct a new building, add to an existing building, alter, renovate, or repair existing buildings or structures, and complete an unfinished area such as a basement, while Kelowna's pages say cosmetic changes such as painting, flooring, replacing baseboards, and resurfacing cabinets do not require a building permit, and direct readers to the building bylaw to see when a permit is required. The pattern is consistent even though the lists differ: structural, envelope, occupancy, and systems work needs a permit, and surface finishes usually do not. Do not guess from another municipality's list, and do not start work on the strength of a verbal assurance. Read the bylaw for the authority where the building sits, and if the project sits near a boundary in the bylaw, ask the authority in writing before you start.
What does a building permit cost, and how long does it take?
There is no province-wide fee or timeline, and this guide states none. Fees are set by each local authority, commonly in a fees bylaw, and they vary with the type and size of the project; Richmond's pages, for example, note new fee increases effective January 1 of each year under its consolidated fees bylaw. Timelines vary the same way: they depend on the completeness of the application, the complexity of the project, and the authority's workload, and some authorities run a fast track only for pre-approved designs, as Kelowna does for infill housing. Anyone quoting you a single BC fee or a single BC timeline is quoting one authority's schedule as if it were provincial. Budget from the schedule published by your own authority, ask what the fee is calculated on, and ask whether the fee is payable on application, on issuance, or in stages. Treat any contractor's fee estimate as a check against that schedule, not as the schedule.
Which edition of the BC Building Code applies to my project?
For most projects, the BC Building Code 2024, which came into effect for projects with building permits applied for after March 8, 2024. The 2018 edition's seismic and adaptable dwelling unit provisions remained in effect for permits applied for before March 10, 2025, and projects for which permits are applied for on or after March 10, 2025 are subject to the 2024 Code including those provisions. In-stream projects, where certain criteria are met, are a defined exception: projects whose drawings were prepared before March 8, 2024 may continue under the 2018 seismic and adaptable dwelling unit requirements provided the building permit is applied for before March 8, 2027 and work continues to completion without interruption. Which edition applies is linked to the permit application date and, for in-stream projects, to the drawing date, so the date you apply can change the rules you build to. Confirm the applicable edition with your local authority at application, and keep the confirmation with the file.
Do I need an architect, an engineer, or a licensed builder?
It depends on the project and on your local authority's bylaw, so this guide states no universal rule. Some authorities require the involvement of registered professionals for specified work: Richmond's pages note that under some situations the city requires registered professionals as outlined in its building regulation bylaw, and Kelowna's application materials include structural and geotechnical schedules and drawings, with Schedule B, Schedule D, and insurance, where applicable. Complex, large, or structurally unusual buildings commonly need professional design and letters of assurance; a straightforward interior alteration commonly does not. Separately, building a new home for sale, or acting as an owner-builder, carries its own authorization and warranty rules in British Columbia, covered in the owner-builder guide linked below. Do not hire on the assumption that a professional is optional, and do not hire one on the assumption that every project needs one. Ask the authority which schedules and letters your project type requires, and get the answer before the drawings are finished.
Can I start work while the permit is being reviewed?
Do not. A building permit is permission to start, and starting before issuance puts the work outside the inspection sequence the permit creates. The review process exists to catch code, zoning, and bylaw problems on paper, where they are cheap to fix; work already built to a non-compliant design is expensive to undo, and an authority can require removal or alteration. The practical sequence is: confirm the project is permitted under zoning and any development permit requirement first, apply with a complete package, answer review comments, receive the issued permit with its list of required inspections, and only then start. If timing is tight, ask the authority whether any part of the work, such as demolition under a separate demolition permit, can proceed on its own application. Never treat a submitted application, a paid fee, or a contractor's schedule as permission to build.